Sunrise Wellfield Development Update

Contract 2 for the Sunrise Wellfield Development Project is nearing completion. The water supply line from the well sites to the future water treatment is being completed today. The access road to the water treatment plant has been built, the intersection of Weston Street and Kingston Street has